Institution report Some description for the institution report

Institution Details View the Institution Details Here

BaseLine Inspection

  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    07 Apr, 2023

    Inspection
    Date

    02 May, 2023

    Construction
    Handover Date

Weekly Inspection

  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    07 Apr, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    07 Apr, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    23 Apr, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    26 Jun, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    03 Jul, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    28 Jul, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    07 Aug, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    22 Aug, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    22 Aug, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    25 Sep, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    16 Oct, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    23 Oct, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    20 Nov, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    27 Nov, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    05 Dec, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    13 Dec, 2023

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    17 Jan, 2024

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    24 Jan, 2024

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    28 Oct, 2024

    Inspection
    Date
  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    DAT contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    04 Nov, 2024

    Inspection
    Date