Institution report Some description for the institution report

Institution Details View the Institution Details Here

BaseLine Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    Girls Pit Latrines

    Boys Pit Latrines

    Staff Pit Latrines

    Everlite contractors
    Mwatibu,Lilongwe,CWED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    19 May, 2023

    Inspection
    Date

    19 May, 2023

    Construction
    Handover Date

Weekly Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    Girls Pit Latrines

    Boys Pit Latrines

    Staff Pit Latrines

    Everlite contractors
    Mwatibu,Lilongwe,CWED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    13 Jun, 2023

    Inspection
    Date

©2022 Education Management Infrastructure Monitoring & Reporting | Powered by