Institution report Some description for the institution report

Institution Details View the Institution Details Here

BaseLine Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    02 May, 2023

    Inspection
    Date

    02 May, 2023

    Construction
    Handover Date

Weekly Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    02 May, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    12 May, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    20 May, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    20 May, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    06 Jun, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    13 Jun, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    30 Jun, 2023

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    External Works (EQUALS Phase 1)

    Den Contractors
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    13 Jun, 2023

    Inspection
    Date