Institution report Some description for the institution report

Institution Details View the Institution Details Here

BaseLine Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    Library and ICT Laboratory block

    Boys Pit Latrines

    Girls Pit Latrines

    Staff Pit Latrines

    External Works (EQUALS Phase 1)

    Fortune Construction Limited
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    29 Oct, 2024

    Inspection
    Date

    29 Oct, 2024

    Construction
    Handover Date

Weekly Inspection

  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    Library and ICT Laboratory block

    Boys Pit Latrines

    Girls Pit Latrines

    Staff Pit Latrines

    External Works (EQUALS Phase 1)

    Fortune Construction Limited
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    28 Oct, 2024

    Inspection
    Date
  • Approved

    Double Classroom Block

    Twin Science Laboratory (EQUALS Phase 1)

    Library and ICT Laboratory block

    Boys Pit Latrines

    Girls Pit Latrines

    Staff Pit Latrines

    External Works (EQUALS Phase 1)

    Fortune Construction Limited
    Mulanje,Mulanje,SHED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    04 Nov, 2024

    Inspection
    Date