Institution report Some description for the institution report

Institution Details View the Institution Details Here

BaseLine Inspection

  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    Girls Pit Latrines

    Boys Pit Latrines

    Staff Pit Latrines

    Adla Construction Limited
    Balaka,Balaka,SEED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    18 Apr, 2023

    Inspection
    Date

    18 Apr, 2023

    Construction
    Handover Date

Weekly Inspection

  • Approved

    Twin Science Laboratory (EQUALS Phase 1)

    Girls Pit Latrines

    Boys Pit Latrines

    Staff Pit Latrines

    Adla Construction Limited
    Balaka,Balaka,SEED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    22 Jun, 2023

    Inspection
    Date

Hand Over Form

  • Approved

    Twin Science Laboratory (EQUALS Phase 1),Girls Pit Latrines,Boys Pit Latrines,Staff Pit Latrines

    Adla Construction Limited
    Balaka,Balaka,SEED

    Construction Start Date

    05 Dec, 2022

    Intended Completion Date

    05 Oct, 2023

    08 Nov, 2024

    Inspection
    Date

    23 Aug, 2026

    Construction
    Handover Date